Case Study: Cluj Court of Appeal Admits Appeal and Upholds Validity of the PUZ Approved in 2007, Overriding the New PUG, and Requires the Mayor to Issue the Building-Zone (Construction) Certificate

Facts Established by the Court

In the case at hand, the plaintiff—owner of a land parcel in the Dâmbul Rotund area of Cluj-Napoca—challenged the Mayor’s refusal to issue a building-zone (construction) certificate. The plaintiff’s land had been regulated under a Zonal Urbanistic Plan (PUZ) approved by City Council Decision No. 524/2007, which defined parcel configurations, access routes, and urban coefficients for the area.

Through City Council Decision No. 493/2014, a new General Urban Plan (PUG) of Cluj-Napoca was adopted, altering the urban regime for the plot and including it in an urbanization zone (UTR ULiu). The new PUG regulations required the drafting of a new PUZ as a precondition for authorizing any construction. It is well-known that preparing and approving a PUZ in Cluj-Napoca is highly complex and time-consuming, and the plaintiff sought to rely on the right to build according to the PUZ approved in 2007.

The Mayor of Cluj-Napoca issued only an informational certificate of urbanism, refusing to issue the construction-purpose certificate, arguing that the applicable urban regime was under the 2014 PUG and that the 2007 PUZ was no longer valid. The plaintiff considered this refusal unjustified and filed an administrative litigation action.

  • The plaintiff invoked administrative litigation procedures outlining remedies against unjustified refusal by public authorities.
  • Urban planning legislation includes provisions that extend the validity of urban zoning documents for ongoing investments.
  • Procedural norms on the legal effect of normative administrative acts and grounds for annulling administrative decisions were also relevant (e.g., insufficient reasoning, conflicting logic, or misapplication of substantive law).

Court’s Reasoning on Investment Initiation and Automatic Extension of PUZ Validity

The Court determined that, under urban planning law, the sole condition required to extend the validity of the PUZ by operation of law was the initiation of investments during the document’s validity period—not necessarily obtaining a building certificate beforehand.

In practice, the plaintiff and neighboring landowners within the 2007 PUZ area had indeed undertaken various urbanization efforts, including:

  • Reconfiguring and merging plots;
  • Subdividing lands to create access roads;
  • Installing utilities in the area;
  • Developing technical and utility infrastructure.

This demonstrated that the PUZ had been implemented in stages since 2007, triggering the automatic application of the legal provision extending the PUZ’s validity until the initiated developments are completed. The Court confirmed that these conditions were met and concluded that the validity of the 2007 PUZ remains in force until the investments are finalized.

Cluj Court of Appeal’s Decision

The Court of Appeal upheld the plaintiff’s appeal, overturned the Cluj Tribunal’s judgment, and ordered the following:

  • The annulment of the building certificate previously issued by the Mayor;
  • The Mayor of Cluj-Napoca is obliged to issue a building-zone certificate in the scope of constructing an individual dwelling, boundary fencing, yard arrangement, and utility connections;
  • The Municipality of Cluj-Napoca is required to cover the legal expenses.

Conclusions and Impact

The ruling has significant implications in urban planning and administrative litigation by clarifying:

  • How the relevant legal provision extends the validity of PUZs when investments have commenced;
  • That PUZ documentation adopted prior to the new municipal PUG may remain applicable in certain scenarios, even after the new PUG comes into force;
  • That a local authority’s refusal to issue a construction-purpose certificate may be unjustified when earlier, valid urban planning regulations remain in effect.

This decision sets a precedent for landowners affected by prior PUZs, affirming that urbanization and infrastructure measures initiated while such documentation was valid are sufficient to preserve the PUZ’s effectiveness over time.

Choose the Brisc Legal team of lawyers from Cluj-Napoca for solving your legal problem.

14-16, Dorobantilor street
Cluj City Center
2nd floor, room 210
400121, Cluj-Napoca